Sourcing Hotel Casegoods from Vietnam: From Shop Drawings to Shipment

Lobby lounge furniture, Kensington Saipan Hotel Resort Project

Hotel furniture orders are different from retail programs. Every project has its own design intent, finish schedule and opening date, and a delay at one step pushes everything after it. This is how a guestroom casegoods order moves through our factories in Ho Chi Minh City, and where buyers can save the most time.

1. The RFQ package (quote in 3–5 days)

A complete package lets us quote in three to five working days. Send:

  • Design intent drawings and FF&E specification sheets
  • The finish schedule, with physical samples if you have them
  • Quantities per room type
  • Hardware specification
  • Target delivery date and destination

We quote FOB Vietnam.

2. Shop drawings (3–7 days)

Our in-house drafting team turns design intent into construction drawings: panel build-up, joinery, hardware positions and packing. First drawings usually go out within three to seven days of award. One consolidated set of comments from the design team saves a full revision round.

3. Finish and material samples

We submit finish and material samples for approval before production. Approve finishes against a physical sample under consistent lighting; screen colors are not reliable for wood stains.

4. Mock-up room (15–30 days)

Our 35-person sample room builds mock-up rooms in fifteen to thirty days, depending on scope. This is the cheapest point to change anything: a drawer height, a handle, a finish sheen. After production starts, the same change costs far more.

Guestroom furniture, Kensington Saipan Hotel Resort Project
Guestroom furniture, Kensington Saipan Hotel Resort Project

5. Production with in-process QC

Each workshop has its own QC manager, and inspectors check parts at every stage, from cutting to finishing. Each buyer’s order runs as dedicated production.

6. Final inspection, packing and shipment

Before shipment we check quantities and run a final inspection against your approved samples. Cartons are designed and printed in our own packaging plant, and each order ships with unpacking and installation instructions.

Planning summary

StepTypical time
Quotation3–5 days
Shop drawings3–7 days
Mock-up room15–30 days
ProductionConfirmed with the quote, by quantity and materials

Recent work includes guestroom and lobby furniture for the Kensington Saipan Hotel Resort Project. See our hospitality furniture page, or send us your drawings for a quote.